Decommissioning Checklist
This checklist is used to ensure the proper decommissioning and disassembly of the AES battery cabinet energy storage system. Additional system-level decommissioning procedures may be required for interconnected equipment.
Disconnection and Safety Procedures
PROCEDURE | CHECK |
---|---|
Open all disconnects | Ensure there is no electrical connection to any externally connected Hybrid Inverter System. |
De-energize internal busbars | Confirm the system is completely powered down and no voltage is present. Use a multimeter for verification. |
Disconnect external power sources | Ensure all AC and DC power sources have been safely disconnected and verified with a multimeter. |
Isolate Battery Packs | Pull the MSD from each battery pack one by one and confirm no voltage is present on battery cables. |
Disassembly of the AES 210HV
PROCEDURE | CHECK |
---|---|
Remove battery cabinet covers | Carefully remove the covers and shields for access to the internal components. |
Disconnect connections | Disconnect all external connections from the battery and inverter. |
Release cabinet anchors | Unscrew and remove all anchor bolts securing the AES 210HV to the concrete pad. |
Remove the battery cabinet | Safely remove the cabinet from its installed location using appropriate equipment. |
Disposal and Recycling
PROCEDURE | CHECK |
---|---|
Recycle components | Recycle all recyclable components in accordance with local and national recycling regulations. |
Dispose of non-recyclable components | Properly dispose of all non-recyclable components according to local waste disposal guidelines. |