NOTE |
|---|
|
Commissioning must be performed by a CEC-accredited installer in accordance with AS/NZS 4777.1 and AS/NZS 5139. |
Pre-Commissioning Checklist
Verify Inverter Firmware is Up-to-Date
Check and confirm that the latest firmware is installed.
-
To see if there is a newer version available:
-
Settings > Device Upgrade
-
Verify System
-
Verify all breakers and isolators (DC and AC) are in the OFF position.
Inspect Connections
-
Verify the polarity of all DC connections.
-
Verify all AC and communication connections are secure and correct.
Inverter Pre-Commissioning
Before starting the system, complete all pre-commissioning checks outlined in the Solis inverter manual. These include:
-
Verify all mechanical and electrical connections
-
Confirm proper ventilation and secure mounting
-
Prepare tools (e.g., multimeter) and the SolisCloud mobile app for setup and monitoring
For complete instructions and app registration steps, refer to the Solis S6-EH3P inverter manual