COMMISSIONING
NOTE |
|---|
Commissioning must be performed by a CEC-accredited installer in accordance with AS/NZS 4777.1 and AS/NZS 5139. |
Pre-Commissioning Checklist
Verify Inverter Firmware is Up-to-Date
Check and confirm that the latest firmware is installed.
To see if there is a newer version available:
Settings > Device Upgrade
Verify System
Verify all breakers and isolators (DC and AC) are in the OFF position.
Inspect Connections
Verify the polarity of all DC connections.
Verify all AC and communication connections are secure and correct.
Inverter Pre-Commissioning
Before starting the system, complete all pre-commissioning checks outlined in the Solis inverter manual. These include:
Verify all mechanical and electrical connections
Confirm proper ventilation and secure mounting
Prepare tools (e.g., multimeter) and the SolisCloud mobile app for setup and monitoring
For complete instructions and app registration steps, refer to the Solis S6-EH3P inverter manual