TIPPING HAZARD
Failure to follow these instructions may result in injury. |
AES 210HV Overhead Hoisting
Lifting Preparation
-
Securely fasten all four lifting lugs into the designated holes at the top of the cabinet.
-
The lifting lug hole diameter is 51 mm (2 in).
-
The crane hook or lifting bar must be at least 900 mm (36 in) above the cabinet.
Hoisting Guidelines
-
Use all four lifting lugs for balanced lifting.
-
Ensure sling connections are secure and sling lengths are equal.
-
Keep the hoisting angle below 10° to maintain stability.
-
Conduct a low-height test lift to verify load stability.
-
Use lifting straps or chains rated for at least 3,000 kg (6,500 lb).
-
Spreader bars may be required to prevent straps from contacting the cabinet.
-
Keep the crane hook at least 1 meter above the cabinet for safe lifting.
-
Lock the cabinet door to prevent accidental opening.
-
Lift and lower slowly to avoid shocks or sudden impacts.
Safety Precautions
-
Keep all personnel at a safe distance during lifting and lowering.
-
Use spotters to guide the cabinet into position and ensure a clear working area.