COMISSIONING PROCEDURE
Pre-Commissioning Checklist
Verify Inverter Firmware is Up to Date
Check and confirm that the latest firmware is installed.
To see if there is a newer version available:
Settings > Device Upgrade
Verify System
Verify all breakers and disconnects (DC and AC) are in the OFF position.
Inspect Connections
Verify the polarity of all DC connections.
Verify all AC and communication connections are secure and correct.
Inverter Pre-Commissioning
Before starting the system, complete all pre-commissioning checks outlined in the Solis inverter manual. These include:
Verifying all mechanical and electrical connections
Confirming proper ventilation and secure mounting
Preparing tools (e.g., multimeter) and the SolisCloud mobile app for setup and monitoring
For complete instructions and app registration steps, refer to the Solis S6-EH3P inverter manual